A lot of labor is involved in construction work in Thailand. Notice the number of people at work here. Photo 8 June 2007. |
|
 |
Beginning of July 2007. Amazingly, the building has already arrived to the 6th floor. It seems like about 10 to 14 days are needing to add a floor. |
|
Construction of Admiral Suites (Construction Site A) is progressing rather smoothly. Work seems to be scheduled nowadays during the day time only, and sometimes during the evening hours. At this pace, the main construction of Admiral Suites will be finished soon.
 |
The iron inside of reinforced cement supporting columns is being prepared. See also picture below. Photo taken beginning of July 2007. |
|
 |
After the wire mesh is placed inside, a mold is constructed, and then cement is poored inside the mold. Beginning of July 2007. |
|
Begin September 2007 :
 |
Not clear how many floors are being built. At present Admiral Suites reaches the 10th floor. Notice the green canvas. According to regulations this is needed to keep the dust in. Not sure whether it is comfortable to work inside it. |
|
October 2007 :
Not much is visibly occurring at the building site. The structure seems to be mostly built. Now the interior work and the walls are being constructed. Probably we will not make many more pictures of this site, and concentrate further on Wind Sukhumvit.